Design of Biogas Power Plant
Design of the Biogas Power Plant in El Salvador
As announced by the
Comisión Ejecutiva Hidroeléctrica del Río Lempa (CEL), we are proud to have
won, together with our German partner Fichtner Water & Transportation GmbH,
the international public tender for the design of the Biogas Power Generation
Plant on the Acelhuate River, El Salvador.
Project Description
Currently, wastewater
from the metropolitan area of San Salvador (AMSS) is evacuated through five
main sewers and discharged untreated into the network of tributary streams into
the Acelhuate River.
This plant aims to
convert a serious environmental problem into a self-sustainable electricity
generation plant. The plant will clean up to 70% of the wastewater from the
AMSS through the Acelhuate River, contributing to the environmental improvement
of the country and at the same time generate electricity.
Main components:
-
Wastewater
Collector.
-
Wastewater
Treatment Plant (WWTP)
-
Biogas
Power Generation
-
Photovoltaic
Generation
-
Small
Hydroelectric Power Plant
-
Electrical
Substation and Transmission Line
-
Complementary
Works
Scope
Preparation of the
final design, detailed engineering and bidding documents for the construction
of the treatment plant (WWTP) and electricity generation from three energy
sources: biogas, solar and hydroelectric.